(4.3) Our achievements

Since the establishment of JSC «Maxsuselektrtarmoqqurilish» the following works have been carried out at the facilities:

Construction of a 220 kV overhead line TashGRES – PS Tashkent

Construction of 220 kV overhead line Karshi NS-7 — Talimarzhan TPP

Construction of 220 kV overhead line Karshi NS-7 — Talimarzhan CCI Construction of a 500 kV Tashkent substation Reconstruction of the 500 kV overhead line Syrdarya SDPP — SS Guzar

Reconstruction of a 220 kV overhead line in the zone of a / highway Tashkent — Chimgan — Charvak

Reconstruction of a / road 4P6 Tashkent — Chirchik — Chimgan — 4P1. Tashkent ring road bypassing the village of Durmen

Transitions and reconstruction of 110 kV overhead lines

Plant of 220 kV overhead line Charvak — Chirchikskaya at 500 kV Tashkent substation

110 kV overhead line construction of a hydroelectric power station at the Tupolang reservoir of the Surkhandarya region

Reconstruction of SS 220/110/10 kV Sary Bazar

Railway electrification Tukimachi — Angren. Reconstruction of intersections of 35-500 kV overhead lines

Substation 500 kV Uzbekistan and 500 kV overhead line Novo-Angrenskaya TPP — Substation Uzbekistan

Construction of a double-track electrified railway line Jizzak — Yangiyer and a single-track electrified railway line Yangiyer — Farkhad. Reconstruction of the intersections of the existing 110 — 500 kV transmission lines

Construction, installation and drilling and blasting operations at the «500 kV overhead line Talimarjan TPP — Substation Sogdiana